August 14, 2019 – 80′ Gangway Arrives

To get from the fixed dock to the new
outside wave attenuator, we selected an
80′ gangway.

It arrived today.

It should be installed later this week.

 

August 6, 2019 – Electrical Updates

 

The trench is being dug across Parking Lot “B” to accommodate

all of the new electrical circuits.  The parking lot should re-open

in a few days.

August 6, 2019 – Updates

Section 3 of the outside dock is in place.

 

Now, we just need the wrench to tighten the bolts…..

 

 

 

 

 

 

Ohhh, there it is!

August 2, 2019 – Wave Attenuator installation Begins

Two sections of the new attenuator/outside dock arrived Thursday.

 

 

 

 

 

 

 

The first section of the replacement wave attenuator is being aligned and installed today, weather permitting.

August 1, 2019 – Wave Attenuator Section 1

Section one of the southern wave attenuator will arrive later this morning by water.

When that section arrives I will post a picture….

 

July 24, 2019 – 1st New Dock Section Arrives

Our first section of dock underwent a traffic test from St. Pete/Tampa.  All went well.

Now the others sections will be scheduled for shipment as they are ready to be shipped.

July 9, 2019 – Electrical work begins on dock 5 in Southern Basin

Marina Utilities, a subcontractor for Brance Diversified, is currently on site for the electrical repairs to Dock 5.  When complete, the dock that is between the boat ramp and Brett’s will be disconnected from the pilings and floated south to be joined to Dock 5.  The amenities will be limited on this longer, connected dock.  Dock 5 is intended to be used as a dinghy and short term location.

A new dock has been ordered and is being manufactured to be installed in the location between the boat ramp and Brett’s.

 

July 4, 2019 – Join us on shore for the 4th of July

Although the marina is closed to boat traffic, come join us and Light Up Amelia on shore for the annual Hometown 4th of July Celebration.  Fireworks will launch at 9:00 PM.

JUNE 24, 2019 – Southern Basin Dredge Project Complete!

So, what’s missing???

The Southern Basin dredging is complete and the equipment is leaving.

 

 

 

 

 

 

 

 

 

Out next step is to complete a post dredge hydro-graphic survey to insure all material removal requirements were met.

June 20, 2019 – Dredging Continues

The staff from Brance Diversified continues to make progress in completing the 50K+ cubic yard dredge project in the Southern Basin.
If all goes well, they will complete this task by the end of June.

The next task for Brance’s crew to work on is the relocation of an existing dock.
The section of dock in front of Parking Lot “B” will be moved to the southern end and married to the dock that is now in place at the southern end.